When my husband and I purchased our house in 2022, the main bathroom had a separate toilet. Apart from the fact that the interior of these two rooms was outdated, the layout was also impractical, and the space was not optimally used. The doors of these two rooms were so close to each other, which…
When my husband and I purchased our house in 2022, the main bathroom had a separate toilet. Apart from the fact that the interior of these two rooms was outdated, the layout was also impractical, and the space was not optimally used. The doors of these two rooms were so close to each other, which made it difficult for someone to exit the bathroom while someone else was leaving the toilet at the same time.
In addition to the above, a hallway closet adjacent to the bathroom ‘stole’ a lot of space which could have been used to enlarge the bathroom instead.
We decided to remove the hallway closet, together with the wall between the main bathroom and the toilet, and finally created a much more spacious bathroom.








Budget Breakdown:
Sanitary ware - On Tap
8950.88
|
Bath - Builders
9917.11
|
Shower panel
5144
|
Vanity and basin - Blue Sky Interiors
10500
|
Floor tiles and grout - On Tap
4556
|
Subway tiles and grout - Italtile
3430
|
Downlighters; fittings; light switch
644.46
|
43141 |
Contractors:
Tri-lectro Cape Town (electrical works)
1742.18
|
Hertz Construction – materials and labour were included in one quote (removed existing door and doorframe; excavation of foundation; prepared foundation for new wall; built new wall; prepared door and frame; hung door; prepared new floor and do topping; installed drainage for new shower and basin; installed new floor; removed old pipes from walls; cut new pipe works in walls and installed new pipes; cut off old plaster and prepared walls for new plaster; plastering and painting of walls; installed new ceiling; tiling of floors and shower; attended to final fitting of basin, shower and bath)
44800
|
46542 |
Grand Total R89683 |